The proposal for the 3G pitch was initially presented in March 2024, with a projected completion date of March 2026.
Over the following two years, significant progress was achieved, particularly in securing community support. A number of local organisations formally expressed their backing for the project.
A grant application for a feasibility study was submitted to the Pen Y Cymoedd Wind Farm Fund in the sum of £15,979.82, which was successfully awarded.
Following this, the necessary preparatory work commenced. This included planning requirements, public consultation, engagement with major development contractors, lighting and noise impact assessments, adjustments to pitch specifications, and various additional compliance and technical matters.
During this period, a full funding application was submitted to the Pen Y Cymoedd Wind Farm Fund for £443,894.18. Additional funding sources were approached, securing approximately 9% of the total project cost.
There was no early indication that the funding application would be unsuccessful. However, as the feasibility study was nearing completion, the Pen Y Cymoedd Fund advised that they were not willing to act as the principal funder.
At that stage, there remained hope that Sport Wales might be able to bridge the funding gap. Unfortunately, this was not possible and, with great disappointment, it was confirmed that the project will not proceed at this time.
Members expressed their sincere thanks to Mr Paul Hinder for his dedication and tireless work on behalf of the Community and the Community Council in progressing this project.
It is hoped that, in the future, an alternative funding source may enable the project to be revived, particularly as substantial preparatory work has already been completed.